Hi guys

Just had a HSE inspection / audit and it was interpreted and agreed to by them and us that lifting equipment has to be inspected 6 monthly by a competant person and must be on some form of schedule.

Testing / PPM / further inspection however is carried out every 12 months by Arjo or equivalent.

So PPM every 52
Inspect every 26

Hope this helps

Paul

(Oh and they wanted to see comprehensive objective evidence that these inspections had indeed been carried out - good old Equipment Management Systems eh ?)