1) Tech finds that job needs parts
2) Tech tracks down details (price etc.)
3) Tech raises request for parts
4) Job becomes "awaiting parts"
5) ... short time passes
6) Parts get ordered (PO raised by Supplies)
7) ... long time passes
8) Parts arrive and get received
9) Parts get issued to the job
10) Job gets completed

Go back and repeat steps 1) to 10)!

How about:-

1) Tech finds that job needs parts
2) Tech selects parts from store
3) Parts get issued to the job
4) Job gets completed
5) Tech raises request to re-stock parts

Go back to 1) and repeat only 5 steps (and job gets completed at step 4)!

Meanwhile, it's back to:-

6) ... short time passes
7) Parts get ordered (PO raised by Supplies)
8) ... long time passes
9) Parts arrive and get received
10) Parts get issued to stock


If you don't inspect ... don't expect.