By the way (before anyone starts howling - and as mentioned before), all my PM procedures carry the default procedure header ("catch all"):-
Examine complete equipment and all accessories to verify
total serviceability. Check mains cable and plug. Check
fuse(s) for correct rating. Carry out electrical safety
tests as applicable. Ensure equipment is clean and fully
fit for use. Leave controls in normal (safe) position.
As well as equipment details, interval in days, estimated time needed for completion (one hour in the case of the post above), and a note about any tools and test equipment needed (and parts if scheduled - although I would only consider scheduling parts for "specific" PM procedures).