Hye guys,
Quite sometime I am not post anything in this forum. Hopefully everyone can still willing to help me.
Is there anyone in this forum experienced installing new hydrotherapy pool in the hospital. I want to know, for technical requirements, what are normally that we need to be focus to.
Thanks guys.
|
|
|
|
|
Joined: Feb 2004
Posts: 14,815 Likes: 72
Super Hero
|
Super Hero
Joined: Feb 2004
Posts: 14,815 Likes: 72 |
You need to make sure that it doesn't leak! Similar construction techniques to a domestic swimming pool.If an overhead hoist is to be included, you need to ensure that its supporting elements are properly constructed, and structurally sound. Also, "wet locations" codes (regulations) apply to electrical supplies, hoists, etc., etc.
If you don't inspect ... don't expect.
|
|
|
|
|
Joined: Jun 2000
Posts: 2,412 Likes: 13
Hero
|
Hero
Joined: Jun 2000
Posts: 2,412 Likes: 13 |
If it's not on the ground floor, I would think the weight would have a significant bearing also.
|
|
|
|
|
Joined: Nov 2007
Posts: 117
Savant
|
OP
Savant
Joined: Nov 2007
Posts: 117 |
They planned to locate at 3rd floor...
|
|
|
|
|
Joined: Feb 2009
Posts: 1,909 Likes: 18
Hero
|
Hero
Joined: Feb 2009
Posts: 1,909 Likes: 18 |
Had 2 hydrotherapy pools planned for construction next year. Plans changed and now we will have 2 Jacuzzi's, 2 underwater treadmills and 2 anti-gravity treadmills instead.
I am not Flippant, I am Smart
|
|
|
|
|
Joined: Feb 2004
Posts: 14,815 Likes: 72
Super Hero
|
Super Hero
Joined: Feb 2004
Posts: 14,815 Likes: 72 |
They planned to locate at 3rd floor...
Not a particularly wise* choice, in my opinion. I wonder what's underneath, on the second - and ground - floors.  And Huw is right ... all that water has massive load bearing implications. Sounds like you need to get a Structural Engineer involved. How large a pool are we talking about here ... full size?  * AKA, "an accident waiting to happen".
If you don't inspect ... don't expect.
|
|
|
|
|
Joined: Nov 2007
Posts: 117
Savant
|
OP
Savant
Joined: Nov 2007
Posts: 117 |
They planned for 5x4m size of the pool with height adjustment platform...
|
|
|
|
|
Joined: Feb 2004
Posts: 14,815 Likes: 72
Super Hero
|
Super Hero
Joined: Feb 2004
Posts: 14,815 Likes: 72 |
Not too big, then ... but still 30 tonnes of water! 
If you don't inspect ... don't expect.
|
|
|
|
|
Joined: Feb 2009
Posts: 1,909 Likes: 18
Hero
|
Hero
Joined: Feb 2009
Posts: 1,909 Likes: 18 |
The 2 swimming pools that were cancelled where due to go on the 7th floor.
I am not Flippant, I am Smart
|
|
|
|
|
Joined: Jun 2009
Posts: 796 Likes: 13
Philosopher
|
Philosopher
Joined: Jun 2009
Posts: 796 Likes: 13 |
" Sounds like you need to get a Structural Engineer involved." Sounds like? I would think that was an absolute certainty !! Could be in the running for "understatement of the year" there Geoff 
Thoughts and information provided on this forum are mine and mine alone and do not necessarily reflect the policy of NSW Health. They may also be complete bollocks!!
|
|
|
|
1 members (daisizhou),
11,519
guests, and
160
robots. |
|
Key:
Admin,
Global Mod,
Mod
|
|
|
Forums26
Topics11,281
Posts74,584
Members10,392
| |
Most Online69,877 Jul 17th, 2026
|
|
|
|